Main Area
imagem-topo

Programme Implementation Structure


At the beginning of its activity in March 2007, Parque Escolar’s objectives included the intervention in 332 schools by 2015.

Under the Initiative for Investment and Employment, new goals were set (between December 2008 and February 2009) for the implementation of the Modernization Programme, namely:

  • Anticipated start of construction of 75 schools covered by Phase 2, through the publication of Exceptional Recruitment Scheme, which in the case of the Parque Escolar has a particular focus on reducing the deadlines set in various stages of the restricted procedure with prior qualifications;
  • Launching the third phase of the Programme with the selection of 100 schools, starting working with schools in setting targets and intervention project, ensuring the public tender for the work, from the first half of 2010.

Thus, the objectives of the Modernization Programme point to the conclusion of interventions in 332 schools by the end of the academic year 2014-2015.